Project Highlights
Aggressive Multi-Phase Delivery: Six phases executed over an eight-month schedule, with one major phase completed in just 17 weeks using 2–3 shifts daily.
Comprehensive Scope: Full demo-to-shell and build-back featuring open ceilings, custom soffit raceways, branded feature walls, breakrooms, and a signature living wall.
Employee Wellness: High-end fitness center with premium locker rooms, coordinated with Exos for facility management.
Seamless Coordination: Integrated efforts with another GC in the building, ensuring scopes aligned and schedules remained intact.
On-Time & On-Budget: Maintaining schedule and budget targets across all phases despite accelerated timelines and complex scope.
Quality Assurance: Early phases completed with minimal punch list items, reflecting rigorous QA/QC standards and client satisfaction.
Aggressive Multi-Phase Delivery: Six phases executed over an eight-month schedule, with one major phase completed in just 17 weeks using 2–3 shifts daily.
Comprehensive Scope: Full demo-to-shell and build-back featuring open ceilings, custom soffit raceways, branded feature walls, breakrooms, and a signature living wall.
Employee Wellness: High-end fitness center with premium locker rooms, coordinated with Exos for facility management.
Seamless Coordination: Integrated efforts with another GC in the building, ensuring scopes aligned and schedules remained intact.
On-Time & On-Budget: Maintaining schedule and budget targets across all phases despite accelerated timelines and complex scope.
Quality Assurance: Early phases completed with minimal punch list items, reflecting rigorous QA/QC standards and client satisfaction.